Construction of New Boundary Wall for the plot adjacent to PARCO/PAPCP Station.
It was a project of infrastructure works. AMC started construction of New Boundary Wall for the plot adjacent to PARCO/PAPCP Station on September 3rd, 2013. The total length of this structure was 1532 RFT. It was completed within its assigned budget and required timeline.
AMC focuses to achieve a distinctive and higher level of construction services while keeping the budget within assigned limits. The construction standards are always kept up to the mark. The efficient struggle by the AMC team makes it the best amidst other construction companies of Pakistan.
Client
P.A.R.C.O
Project Location
Karachi, Pakistan
Nature of Works
nfrastructure Works, Boundary Wall Works
Length of the structure
1532 RFT
Number of Storeys
N/A
Date of Award
03.09.2013
Stipulated Date of Completion
05.11.2014
Date of Completion
05.11.2014